Dover Discovery Centre
The Dover Discovery Centre refurbishment highlights Jager’s expertise in executing complex, multi-system electrical upgrades on a major cultural facility, achieving all client objectives and certification requirements.
Project Details:
Client: Walker Construction (UK) Ltd
Duration: 14 months
Location: Dover, Kent, UK
Objectives
Complete Stage 5 electrical design and installation in line with the main refurbishment programme
Upgrade primary distribution to support the centre’s expanded capacity
Deliver modern lighting, power, safety and security systems
Scope of Works
Installation of an 800 A switch-fused isolator and main panel board
Split-metered TPN distribution boards for lighting and power
Internal and external LED lighting with presence and daylight controls
Small-power outlets and structured data cabling
Fire alarm system with detectors, call points and sounders
Automatic Opening Vents (AOV) integration and disabled refuge intercom
Access control, CCTV, intruder and panic alarms
Lightning protection and earthing upgrades
Key Challenges
Phased shutdowns to suit multiple trades without delaying the overall programme
Fitting large distribution equipment into restricted plant-room spaces
Integrating electrical, fire and security systems for seamless operation
Outcomes & Benefits
Delivered on time within the 14-month schedule
Enhanced energy efficiency through networked lighting controls
Modern safety and security systems providing full compliance and peace of mind
Future-ready power distribution designed for expansion