Dungeness Power Station Storage Facility
The Dungeness project underscores Jager’s capability to deliver complex refurbishments under demanding environmental and safety constraints, ensuring reliable operations for critical infrastructure.
Project Details:
Client: Walker Construction (UK) Ltd
Duration: 5 months
Location: Dungeness, Kent, UK
Objectives
Rewire the old hall and install new distribution equipment within five months
Provide efficient lighting and power tailored to storage operations
Ensure compliance with site-specific safety procedures
Scope of Works
New 500 A incoming supply and main distribution board
Sub-distribution via TPN and SPN boards for lighting, power and plant feeds
High-efficiency LED strip and bulkhead luminaires with integral emergency modules
Galvanised steel trunking and ladder rack containment
General-purpose sockets and dedicated circuits for plant equipment
Emergency escape lighting and illuminated signage
Enhanced earthing and bonding to site requirements
Key Challenges
Maintaining segregation and controlled access in an active works environment
Routing cables to minimise disturbance to protected wildlife habitats
Installing equipment within limited headroom and tight spaces
Outcomes & Benefits
Completed and commissioned on schedule with zero defects
Distribution network designed for 20% future load growth
Improved safety metrics through upgraded containment and emergency lighting