Finberry Primary School (Phase 2)
Phase 2 at Finberry Primary illustrates J.A.G.E.R’s commitment to safety, timely delivery and quality, even under pandemic constraints.
Project Details:
Client: Baxall Construction
Start Date: June 2020
Duration: 5 months
Contract Value: £121,000
Location: Finberry, Ashford, Kent
Objectives
Expand school facilities with eight classrooms, resource centre and nursery
Install robust life-safety and IT infrastructure
Maintain safe working conditions during the COVID-19 pandemic
Scope of Works
Small power and LED lighting
Addressable fire alarms
Data cabling for classrooms and offices
Access control, CCTV and intruder alarm systems
Key Challenges
Strict health-and-safety measures amid pandemic
Coordinating M&E with ongoing school operations
Achieving full functionality in five months
Outcomes & Benefits
Zero-defect handover
All deadlines met without incident
Enhanced learning environment with modern IT and safety systems