High Halden

Our first project in partnership with Murston Construction Ltd began in January 2023. We were contracted to carry out the full electrical install for 28 new homes. This project also includes EV car charger installation, as Jager embrace the move towards greener energy, which can help to reduce the carbon footprint.

Project Details:

Client: Murston Construction Ltd
Start Date: January 2023
Completion: January 2024
Location: High Halden, Kent

Objectives


  • Provide full house electrical installations for 28 homes

  • Install EV charging points to support sustainable transport

  • Complete within a 12-month development programme

Scope of Works


  • Main distribution and house wiring

  • Lighting and small power

  • EV car charger installation

Key Challenges


  • Sequencing electrical handovers to match house completions

  • Ensuring compliance with EV charging standards

Outcomes & Benefits


  • All homes delivered with EV chargers installed

  • Enhanced appeal through future-proofed infrastructure