Riverside Park (Phase 1, 2 & 3)

Riverside Park showcases our capacity to sustain large-scale, multi-phase residential programmes with stability and high quality.

Project Details:

Client: Gravel Rock / Quinn Estates
Start Date: January 2018
Completion: October 2023
Contract Value: £7,000,000
Location: Ashford, Kent

Objectives


  • Install MEP services for 26 townhouses and 246 apartments over three phases

  • Embed renewable technologies including PV across the development

  • Maintain continuity across successive contracts

Scope of Works


  • Power distribution and LED lighting

  • Fire alarm installation

  • PV panel installation

Key Challenges


  • Managing phased handovers while residents occupied completed units

  • Coordinating with multiple stakeholders over several years

  • Ensuring consistent quality across all phases

Outcomes & Benefits


  • Seamless delivery of 272 units with no major defects

  • PV installations contributing to sustainable operation

  • Projects completed on time and to budget